Honduras Hope Mission has worked in La Villa de San Francisco for 20 years. In the spring of 2023, as part of our ministry there, we completed the construction of Hope Center, which is used for educational and social programming for families in the community. We are in the process of erecting a water purification system at that facility. Thus far, with the funding from Ingomar Living Waters and others, we have installed two 9,000-gallon storage tanks and the accompanying pumps and filters.
See Project 2023-054.
However, we have determined that a third tank and additional filters are needed to store and treat the water properly.
The original two-tank system was designed to capture an entire year of rainwater, while also distributing 130 gallons per day. We never contemplated processing city water; the design was only to purify rainwater. We ran an analysis at the time, trying to rightsize the tanks. The math assumed a typical amount of rain during the entire year, and the surface size of the roof at the Hope Center. We determined we could distribute 130 gallons of processed water daily. However, because the rainfall is heavier during certain months of the year, we needed to have tanks large enough to capture all that water, much of it over only 2-4 months. The two 9,000 tanks were designed to capture all the rainwater at the peak of the rainy season, filling the tanks and eventually running the tanks to empty, so that we could clean the tanks once a year, during the dry season.
Much to everyone’s surprise, the instructions for the pump system included three tanks, not two. Distributing 130 gal of water per day, we would have been storing water in the two tanks for too long a time. The water’s color and smell would change, and even though it was purified, people would not drink it. The recommendation is for an additional filter system. With this system, we only need a third tank of 500 to 600 gallons. It will include an additional filter system that will enhance the one already in place, and we have been assured it will be able to purify the city’s water. The pumps in place now are very powerful and can move a lot of water. However, they must be run manually. The revised system will be automated. We will have the ability to fill a third tank 7-8 times a day, and pump out 4,000 gallons or more in 8 hours, assuming we have daily access to city water.
The city water will run through all three tanks and both filter systems. Historically, there have been times each year when water has not been available from the city each day. We will take advantage of those days when it is available, and put as much into tanks one and two as we can. Nevertheless, we may have to adjust output on those days and weeks.
Having this third tank will greatly increase the system’s capacity, enabling up to 4,224 gallons of water to be purified daily. Not only will we treat and distribute rainwater, we will be able to treat and distribute water from the town’s water system, providing up to 2,000 people with two gallons of purified water daily. Projected costs for the chlorine, aluminum sulfate, granular activated carbon, sand, gravel, filters, ultraviolet, and ozone lamps required to provide 4,000 gallons of purified water daily are approximately $16 per day. This will be recouped by charging those who receive the water a small amount. (1 lempire per 5 gallons of water distributed will yield $30 per day. Note that vendors in town charge 30 lempires per 5 gallons.)
This additional storage tank and filtration system will enable the Honduras Hope Mission to provide water not only to all of our families who use the Hope Center facility each week, but with the addition of water from the town’s water supply, we will be able to provide purified water daily to as many as 2,000 individuals who live near the Hope Center.
PROJECT-SPECIFIC COSTS AND FUNDING INFORMATION
Total project cost: $15,000.00
Cost breakdown:
Materials & Labor: $15,000.00
Administrative: N/A
Future maintenance: Filters, lamps, and other supplies listed above will be paid for with the funds received from the sale of the water
Amount of funding requested: $15,000.00
PROJECT TIMELINE
Estimated project start date: September 1, 2025
Estimated project completion date: September 30, 2025
Honduras Hope Mission provides biblical training to 34 Hope and Promise families each week. In addition, during our annual medical mission, Bibles are distributed to those who come to the medical clinics, and individuals are given the opportunity to meet with the pastors of the churches who host us. We will offer the same opportunity to all those in the community who come to our facility each day to receive water.

On the left is water before the filtration system. On the right is purified water distributed to taps at Hope Mission Center.
Back in 2023, a water collection, filtration, and treatment system was installed at Hope Mission Center (see 2023-054 for details). However, after a couple months of operation, two issues were discovered. First, many more local villagers wanted access than originally planned for and even with two very large storage tanks, the system could not store enough water during wet season to last all the way through dry season with so many local villagers drawing clean water at Hope Mission Center. And second, after water was buffered for a couple months in the large holding tanks, it began to take on a stale and foul smell and taste. The water was tested and it was still safe to drink. But nobody wanted to drink it!
So in 2025, generous ILW WORLD CHANGERS made Phase II possible. In fall 2025, Phase II was started to take local (dirty) municipal water as input to greatly expand the water intake year-round and also increase the storage and filtration capacity of the system. This was necessary to handle the needs not only of around 130 Hope Mission Center users but also up to 2,000 surrounding village people.
The construction of the expanded Phase II filtration system was begun in the fall and completed in late December 2025. Taxes and tariffs on imported components were higher than expected driving cost from $15,000 total up to $16,019.84. Hope for Honduras Mission covered the difference (thank you!). On January 10, 2026, the installation team finalized the operations manual and coordinated a staff training program which several Honduras Hope Mission individuals attended. On the same date, a water sample was taken and delivered to a government approved water testing lab, Laboratorio de Analisis Industriales MQ. We received a notice on January 16, 2026 that the water quality was approved for drinking purposes.
Then, on January 31, 2026, our Honduras Hope Medical brigade, the medical mission team from Pittsburgh, ceremonially cut the ribbon to begin the water distribution program. Today, there are many happy people in La Villa de San Francisco in Honduras. And now Phase II is complete! So now all of the surrounding village can come and draw clean water without having to worry about the storage tanks running out during dry season. And now everyone can enjoy fresh clean tasting water without having to deal with bad tastes and smells.
Dr. Rob Potter, leader from Honduras Hope Mission, is the first to drink from the new expanded storage and treatment system at Hope Mission Center.
Participants on the annual medical mission trip celebrate the opening of the new clean water system with staff and students and local villagers at Hope Mission Center!
It is amazing what Ingomar Living Waters WORLD CHANGERS have done. In both 2023 and 2025, giving to water filters for Honduras exceeded need providing excess funding that helped make this more permanent clean water solution and Hope Mission Center possible. Thank you to all of the WORLD CHANGERS who have helped to bring the gift of clean water to La Villa de San Francisco! And thank you Honduras Hope Mission for not only healing the ailments caused by dirty water in Honduras but also helping to address the root cause by bringing them the gift of clean water!