MKHOTA VILLAGE, MALAWI

COMPLETE

STATUS

people impacted

dollars funded

FUNDED SEPTEMBER 4, 2025

LOCATION

Mkhota Village is located in the Traditional Authority Chikulamayembe, Rumphi district, Malawi.

CURRENT CONDITIONS

The people of Mkhota village suffer from a lack of clean water within reach. [Water is usually fetched either by] men cycling with containers or carrying water on their heads over a long distance, or by women carrying big buckets on their heads while carrying babies on their backs. This reduces people’s time and productivity.

In a desire to ration water, the villagers subject themselves to less hygienic strategies, making them prone to many bacterial infections. The most prevalent of these are cholera, especially in the wet season, diarrhea, and sometimes bilharzia.

Girls and boys from the nearby school take turns to fetch water for the rest of the school to drink on a particular day. They have no option, but to miss classes for the sake of all.

OUR EXPERIENCE IN THE AREA

We have worked with Water for Life, a drilling company based in Lilongwe, the capital city. They have offered the best services so far. It is also good to mention that communities have been very supportive, offering any assistance needed. Men and women gather at the drilling site to witness the dawn of the new era.

FUTURE MAINTENANCE AND REPAIRS

Once funded and we have the project done, we will form a committee of consumers that will be benefit from the water. They will make a yearly affordable contribution. The parish will be taking care of the difference to make sure the pump is always functional.

CHRISTIAN DISCIPLESHIP

This water is to be given to the villages regardless of religious affiliation. Village headmen will help oversee the care of the well, ensuring that no one is prohibited. There is a nearby church. The site chosen is for convenience. We know and are very much aware that such projects have been part and parcel of evangelization. They make a huge impact on the Christian disciple-making outreach. They form a holistic approach to evangelization. This project is likely to do more in this catchment area.

Fr. Edmund Nyoka drops a pin at the proposed well site.

PROJECT DETAILS AND TIMELINE

Project Scope: A borehole well with a hand pump

Total Project Cost:  $5,000 (MK 8,750,00) 

Funding Requested from ILW:  $4,000

Other Funding Sources: The Catholic Diocese of Pittsburgh will supply an additional $1,000.

Future Maintenance: K1000 per person per year. ($0.57)

Date Funding Required: 1 November 2025

Estimated Project Start Date: 15 November 2025

Estimated Project Completion Date: 20 November 2025

YOUR IMPACT

This clean water well will reduce the distance that people travel to source water, enabling them to be more productive. It will improve the health of the members and  students in the nearby school, who will also benefit from the well.

COMPLETED APRIL 24, 2026

We have successfully drilled and installed a pump in Mkhota. There is plenty of water, and the villagers are all smiles.

We delayed to implement the project because of a problem in the funds reaching us. We still managed because we engaged the driller, basing on our working relationship, to understand our situation. At this time the cost of the drilling had risen sharply due to the rise in the cost of the fuel at the pump, but Ingomar Living Waters’ amount has not changed. The church picked up the balance.

The chief of the area was all smiles and very grateful. One woman narrated that since she has a problem with legs, she can hardly go far to get water to drink. When children are at school, she had the most difficult time as she had no one to send. Now she can walk to the pump herself.

PROJECT COMPLETION REPORTMKHOTA VILLAGE MALAWI
Report Submission Date:April 24, 2026
Actual Project Completion Date:April 5, 2026Has the Completion Date Changed Since Funding Was Approved?:It has. There was a hiccup in the funds reaching us.
We had to follow up with the central bank, leading to
the delay [starting the work].
Total Actual Project Costs
from Beginning to End:
$5,085Have Costs Changed Since Funding Was Approved?:Yes, the cost has changed due to the risen cost of fuel. It is now $5600. But we were able to do at this cost because we have built a working relationship with
the driller, and explained our delay situation and
the impact on the cost.
Updated Estimate of the Number of People Who Actually Will Be Served Daily:1,400Has the Estimate Changed
Since Funding Was Approved?:
No
Actual Measured Pump Capacity
in Liters Per Minute (LPM)
or Gallons Per Minute (GPM) :
60 LPM  |  15.850 GPMDepth of Well in Meters or Feet:42 Meters  |  137.8 Feet
Actual Latitude, Longitude:-11.009685, 33.658585Has Location Changed Since Funding Was Approved?:Yes. Slightly due to the geological survey results,
also because the land has crops, and it was rainy.
We moved only 35 meters from the first spot.

 

BEFORE

AFTER

A message from Fr. Nyoka about the delays in this project:

It has been tough time, for you and for me, waiting for this well to be drilled. The geological survey discovered great water problems in the ground initially, but after two days of survey work, we finally got the spot!  

I hired the first driller, but the compressor had a breakdown. I engaged a second driller, but his price was high, as fuel costs have risen following the Iran war, and I had to negotiate with the third. He accepted to do the work for me, because I have given him business before. As you know, the well was supposed to be made ready last year. In between fuel prices have gone up twice.  Before he came to the site, he had to wait for the water to subside. It has been raining heavily.  He could get stuck. 

That sadness is gone today. We are now happy to have it drilled. For the good news to the donors, for the joy of the water users. Maybe God wanted it to be an Easter gift!  Alleluia!