COMPLETE
LOCATION
Kitukura Village, Uganda is in the Kijonjomi Parish in Isunga Sub-County, Kagadi District. It is one of the larger villages, with over 200 households and a trading center. There are also two churches here and a nearby health clinic.
CURRENT CONDITIONS
They don’t have any clean water sources nearby and instead must rely on open ponds in swampy areas and buying water which usually only the shopkeepers and the clinic can afford to do. The swamps are surrounded by farms. The farms use pesticides, which also get into the water. So the people aren’t just facing the usual issues associated with surface water, but also poisons in the water.
It is good that the clinic is nearby, since the villagers commonly suffer from typhoid, diarrhea, and skin infections. Sile they don’t have to incur the costs of travelling to a clinic, they do still have to pay for medications to treat typhoid, which can be very expensive. So, the poverty costs of dirty water are high.
Another issue is that these types of water sources tend to dry up during the dry season, causing the women and children to travel further and further away from the village center as they search for open water sources. During the rainy season, many are walking over 2.5 kilometers. But in the dry, it could take hours just to find a source of water. If the dry season is particularly bad, they will have to compete with wild animals, herdsmen, and even other villages for access. And being so far outside of the protection of the village makes them vulnerable to traffic accidents and sexual assault. To try and counter the risks, the women gather and travel in groups twice a day to get the water, as it is too dangerous for them to travel through the bush alone. The children are typically too sick to go to school, or they are helping carry water from the swamps, so they aren’t in school as they should be.
CEED’S EXPERIENCE
CEED has been drilling in Uganda for over 20 years, with over 1,000 wells done to date. The first well was drilled using the percussion method, which could drill inches in a day. A few years after the first well was dug, one of our donors saw the process and felt the call to donate 2 mobile drills for our use which could now drill a well in days. In 2023 we introduced our new big rig for use in areas where we encounter rock layers or other obstacles that the smaller drills cannot overcome, giving us one of the most versatile drilling fleets in East Africa.
The team is Ugandan-staffed and led through the efforts of Herbert Asiimwe, the Director of CEED Uganda. Herbert has been leading these drilling teams for over 15 years, and most of our drillers have been with CEED for over a decade. We make sure we pay our workers good wages in Uganda. After all, the workman is worth their wages, and one of CEED’s goals has always been to ensure that those working for us can support their families through the work they do.
Each well is individually funded, some from the USA and some from inside Uganda, as the Big Rig is contracted by the local government officials and schools. The proceeds from those wells go back into drilling in the poorer, remote villages. But over 80% of the rural population in Uganda still lacks access to clean water, so the work is still great.
Herbert Asiimwe is a licensed CPA, so he does his best to keep the operating costs as steady as he can. And oversight is done in the US office by both Kate Kuzko and the CEED board monthly.
We have spent many years finding the best way to drill, the best materials to use for long-lived wells, and the best way to engage the community both to keep the well running, and to keep it clean and
healthy.
WELL MAINTENANCE & REPAIRS
The funding for future repairs and maintenance is taken care of through a process we have developed over two decades of drilling. When the village is chosen for a well, they sign a contract stating that they will do their best to set aside a few pennies per month to help cover the cost of future repairs. They can do this by selling surplus water to local farmers, or by having a collection. The money is kept at the local bank, and CEED will request periodic checks on the accounts to make sure that the village is taking its responsibility seriously.
This method acts as a guarantee that the village will take ownership of the well. When something is wrong, they have the responsibility to reach out and let us know so the wells can be repaired in a timely manner. Without this process, the village would not take full ownership of the well. We have seen this in villages where other NGO’s come in to drill but leave without putting a plan of ownership in place. Those wells often break from small fixable issues, but the villages don’t contact anyone it ‘wasn’t their well’ and they thought the NGO’s would come back. The committee and the water fund solved this issue, and none of the wells we have drilled over time have fallen into disrepair.
CHRISTIAN DISCIPLE-MAKING
We typically try to drill as close to churches as we can, but even if there isn’t already a congregation planted in the area, the well plaques themselves also share scriptures, and the people know that the well was given to them by people who love them because Christ loves them.
And we always share the Jesus film when we drill as well, played on a solar-powered projection system in the local dialect. Every month, we hear stories of Ugandans who accept Jesus as their savior through seeing the life of Jesus in their own language.
Our team reports that 2-3 people a week tell us that they have found the Lord after watching this film. Each rig has its own projection system, so no matter where or how we are drilling, we are sharing the gospel.
PROJECT COSTS AND TIMELINE
Total Project Cost: $5,000 for a borehole well and hand pump.
Cost Breakdown:
Materials: $3,900
Labor: $650
Administration: $450 – includes the costs of finding the wells for the application, photography costs, ongoing project management, etc. It goes directly to the work required to manage this specific well and not to any other project.
Future maintenance: Covered by funds raised by the Water Source Committee
Other Funding: Each project is directly funded. We only bring in outside funding sources in case of a dry well or a larger project that we know going in will require more heavy-duty equipment. We don’t anticipate this here. If the big rig is needed, Herbert has funds set aside to meet any overhead, although, since the rig belongs to us, overhead is usually a small cost. We do this so we can keep the U.S. costs as steady as possible for our Donors.
Funding Requested from ILW: $5,000
Date Funding Required: As soon as possible.
Estimated Project Start Date: 2-3 weeks after funding is received in the US office
Estimated Project Completion Date: 2-3 months after the project starts, to allow time for cementing and commissioning.
YOUR IMPACT
This village is already on the path to prosperity with the trading center and the clinic. If they had clean water as well, then they would be able to grow in health. The villagers would be able to work to better support their families with the addition of clean water. There would be more crops grown and more being sold in the trading center. The clinic would flourish with clean water nearby, meaning the workers there would be able to use the water to treat patients rather than relying on shipments.
The women would be able to do more at home and in the fields, not having to look for water during the dry season. The children would go to school. The two churches in the community would grow as the village grows and as outsiders learn about the place where the water is clean.
Often, the neighboring villages learn about CEED and request a well themselves, so one well has ripple effects out into the larger community.
The well is finished, and the Kitukuran people have clean water! The village sent a thank-you letter, specifically from the residents, but there are additional households living outside the village, who share in the blessing of clean water, but are not included in this letter.
We residents of Kitukura village with much pleasure hereby extend our sincere thanks to our donor for the big gift of our borehole donation. It has been for so long since our existence without safe clean water as we could share water from ponds, swamps, rivers with both wild and domestic animals putting our lives prone to diseases like cholera, typhoid, malaria and more so walking long distances for clean water. But with your donation, we are able to acquire safe clean water, improve on our household by hygiene.A population of 800 people which has been depleting forest to get firewood to boil water is now able to get safe clean water from your donation and more so saved the depletion of forests. May the Almighty God bless you abundantly.
| PROJECT COMPLETION REPORT | KITUKURA VILLAGE | UGANDA | |
| Report Submission Date: | September 4, 2025 | ||
| Actual Project Completion Date: | August 22, 2025 | Has the Completion Date Changed Since Funding Was Approved?: | No |
| Total Actual Project Costs from Beginning to End: | $5,000 | Have Costs Changed Since Funding Was Approved?: | No |
| Updated Estimate of the Number of People Who Actually Will Be Served Daily: | 1,400 | Has the Estimate Changed Since Funding Was Approved?: | No |
| Actual Measured Pump Capacity in Liters Per Minute (LPM) or Gallons Per Minute (GPM) : | 30 LPM | 7.925 GPM | Depth of Well in Meters or Feet: | 30.48 Meters | 100 Feet |
| Actual Latitude, Longitude: | 00.935586, 030.865493 | Has Location Changed Since Funding Was Approved?: | No |

All projects are made possible by World Changers.