COMPLETE
LOCATION
The village of Kambugu, in Kicucura Sub Couty, Kagadi District of Uganda, sits at a crossroads where a trading center can be found. The village has 150 households, 4 churches, and 2 schools nearby.
CURRENT CONDITIONS
The closest clean water source is over 4 kilometers away and too long a journey for the women and children who are typically tasked with collecting water for their families. So instead, the village relies on water from a large pond dug into the field. The pond has a grid of logs across the top to try to prevent another drowning, as the village lost a child earlier in the year.
Not only is the pond contaminated with bacteria that cause diseases like typhoid, but it is also contaminated with the fertilizers used to grow the local crops. The combination makes the villagers very sick. They frequently suffer from typhoid, stomach aches, diarrhea, and other illnesses from drinking the contaminated water. The adults are often too sick to work, and the children are too sick to go to school. Despite the logs across the pond, the adults worry that the children will still find a way to fall into the pools of water and drown.
These villagers live in a cycle of poverty and illness that they don’t have the means of escaping on their own. For most families, any income that would have been set aside for school fees, better housing, better food, etc., will instead cover treatments for typhoid and malaria.
They know that without even the dirty water, they would die in days, and they know that with the bad water, they will likely be sick. But they have nothing else.
A village man describes many problems with the water source,
including contamination from bacteria, pesticides, and accidental drowning.
CEED’S EXPERIENCE
CEED has been drilling in Uganda for over 20 years, with over 1,000 wells done to date. The first well was drilled using the percussion method, which could drill inches in a day. A few years after the first well was dug, one of our donors saw the process and felt the call to donate 2 mobile drills for our use which could now drill a well in days. In 2023 we introduced our new big rig for use in areas where we encounter rock layers or other obstacles that the smaller drills cannot overcome, giving us one of the most versatile drilling fleets in East Africa.
The team is Ugandan staffed and led through the efforts of Herbert Asiimwe the Director of CEED Uganda. Herbert has been leading these drilling teams for over 15 years and most of our drillers have over a decade of experience each, and most have been with CEED for over a decade. We are sure to pay our workers good wages in Uganda. After all the workman is worth their wages, and one of CEEDs goals has always been to ensure that those working for us can support their families through the work they do.
Each well is individually funded, some from the USA and some from inside Uganda. The Big Rig is contracted by the local government officials and schools. The proceeds from those wells go back into drilling in the poorer, remote villages. But over 80% of the rural population in Uganda still lacks access to clean water, so the work is still great.
WELL MAINTENANCE & REPAIRS
The funding for future repairs and maintenance is taken care of through a process we have developed over two decades of drilling. When the village is chosen for a well, they sign a contract stating that they will do their best to set aside a few pennies per month to help cover the cost of future repairs. They can do this by selling surplus water to local farmers, or by having a collection. The money is kept at the local bank, and CEED will request periodic checks on the accounts to make sure that the village is taking its responsibility seriously.
This method acts as a guarantee that the village will take ownership of the well. When something is wrong, they have the responsibility to reach out and let us know so the wells can be repaired in a timely manner. Without this process, the village would not take full ownership of the well. We have seen this in villages where other NGO’s come in to drill but leave without putting a plan of ownership in place. Those wells often break from small fixable issues, but the villages don’t contact anyone it ‘wasn’t their well’ and they thought the NGO’s would come back. The committee and the water fund solved this issue, and none of the wells we have drilled over time have fallen into disrepair.
PROJECT COSTS AND TIMELINE
Total Project Cost: $5,000 for a borehole well and hand pump.
Cost Breakdown:
Materials: $3,900
Labor: $650
Administration: $450 – includes the costs of finding the wells for the application, photography costs, ongoing project management, etc. It goes directly to the work required to manage this specific well and not to any other project.
Future maintenance: Covered by funds raised by the Water Source Committee
Other Funding: Each project is directly funded. We only bring in outside funding sources in case of a dry well or a larger project that we know going in will require more heavy-duty equipment. We don’t anticipate this here. If the big rig is needed, Herbert has funds set aside to meet any overhead, although, since the rig belongs to us, overhead is usually a small cost. We do this so we can keep the U.S. costs as steady as possible for our Donors.
Funding Requested from ILW: $5,000
Date Funding Required: As soon as possible.
Estimated Project Start Date: 2-3 weeks after funding is received in the US office
Estimated Project Completion Date: 2-3 months after the project starts, to allow time for cementing and commissioning.
YOUR IMPACT
The local church congregation is ready to be the home of the new well. The church will grow with the addition of clean water. People will come to the well, and eventually come to the services. The other 3 churches will benefit as well as the two schools, as the children grow healthy enough to attend, and parents from further out start to send their children as well.
Statistically, we know that even just 6 months after a well goes in there will be an average 70% decrease in illnesses per day in the village. That means that families will stop contracting illnesses every other month, and many may not fall sick from the old waterborne illnesses at all in a year. The result is that they will be spending less money on medicine and more money on education, food, buildings and community development. By decreasing waterborne illness, you are decreasing poverty.
And the local children will have the chance to go to school. There is no public education in Uganda. Every child who is in school must pay tuition to be there. School supplies are an additional fee as well. Many schools have uniforms, though they do allow for poorer students to come in what they have. If a family is healthier, then they can afford for the children to go to school, or learn a trade and come back and support the family better.
If we were to revisit this village a year after the well started providing water, we’d find a cleaner village, with children on their way to school. There would be flowers and plants in front of businesses, the atmosphere would be happier. The people would look healthier, and the air of despondency would have been lifted. There is nothing quite as drastic as the change clean water can make in the lives of these villages.
We residents of the above-mentioned area do hereby extend our sincere gratitude to our donor for the gift of a borehole donated to our community. It’s of great pleasure that since our existence, we have never had safe clean water, a situation that we have been sharing water from ponds, swamps with both domestic and wild animals rendering our lives to diseases like cholera, malaria, typhoid, skin rashers and others.
With this donation, we are able to get or acquire safe, clean water, improve on our hygiene in our families.
A population of 1500 people has elected a water source committee and forest depletion is to be solved as the hunt for firewood to boil water is solved by the well.
May the Almighty God bless you all abundantly.
THE CONSTRUCTION PHASE
| PROJECT COMPLETION REPORT | KAMBUGU VILLAGE | UGANDA | |
| Report Submission Date: | September 4, 2025 | ||
| Actual Project Completion Date: | September 3, 2025 | Has the Completion Date Changed Since Funding Was Approved?: | No |
| Total Actual Project Costs from Beginning to End: | $5,000 | Have Costs Changed Since Funding Was Approved?: | No |
| Updated Estimate of the Number of People Who Actually Will Be Served Daily: | 1,500 | Has the Estimate Changed Since Funding Was Approved?: | Yes |
| Actual Measured Pump Capacity in Liters Per Minute (LPM) or Gallons Per Minute (GPM) : | 45 LPM | 12 GPM | Depth of Well in Meters or Feet: | 40 Meters | 130 Feet |
| Latitude, Longitude: | 1.032482, 31.091632 | Has Location Changed Since Funding Was Approved?: | Yes, 1 km north of original location. |
THE COMMISSIONING CELEBRATION