LOCATION
Nyarubele is a very small village with approximately 3,210 residents in the Geita Region of Tanzania. The nearest airport is MWZ – Mwanza, located 77.6 km north of Nyarubele. Nearby towns include Kadasi (1.9km south) and Ligembe (7.4km east.)
[Distances are “as the bird flies” and approximate.]
CURRENT CONDITIONS
St. Anthony of Padua Catholic Parish is in the village of Nyarubele. The parish priest, Father Silas Haki, explained the situation of the lack of water in Nyarubele. Since there is no source of clean water, the people must either buy water from the Kabaka hand-dug well or get [dirty, contaminated] water from ponds that are formed during the rainy season. The water from Kabaka is too expensive for most villagers, and they would need to travel 2-5 kilometers each way on foot or bicycle to get it (IF they own one!) Note that hand-dug wells do not provide safe water because of contamination factors, and they dry up completely during dry season.
The Nyarubele people live in such severe poverty that few of them can afford to buy water or even travel to buy water. Most people are uneducated and sustain their families through small agricultural activities and raising livestock to consume and occasionally sell. They walk several kilometers to church, the ponds, and other places every day. A few people have simple bicycles for transportation, and even fewer own a motorized vehicle.
Nyarubele has a clinic. A St. Anthony parishioner is also the nurse at the local clinic. She reported that the people suffer from many waterborne illnesses. The most common are diarrhea, cholera, typhoid fever, dysentery, hepatitis A, amoebiasis, and E. coli. Diarrhea is the fourth leading cause of death in Tanzania. Since it is mainly women and young girls who are tasked with fetching water, they suffer [most] greatly.
FUTURE MAINTENANCE AND REPAIRS
Father Silas Haki explained that currently, the parish is purchasing water from the Kabaka family-owned hand-dug well. This water must be boiled for several minutes before it is safe to drink. Mama Kanuti rides a bicycle to buy water. The parish uses approximately 120 liters of water per day. The cost is about 410,000 TSh ($155) per month. Once the water well project is completed, Father Haki will use the money currently being spent to purchase water to establish a maintenance fund. After several months of doing this, he will have his
maintenance fund. Since this village is truly “the poorest of the poor,” he will not be able to depend upon the parishioners or local people to sustain the funds. Also, for the protection of this water project, the distribution points will be only on parish property. However, it will be open to all who come for water. No one will be denied access to this clean water source, due to religious differences.
Children carry the heavy water home on their heads.
CHRISTIAN DISCIPLESHIP
The water distribution point for the well will bring people together from different walks of faith. Some will not know about the Gospel; some will know, but have doubts about a good and loving God that seemingly does not care for them, and some will come with their faith and trust in God. The people will sometimes interact, and the faithful will share their love for Our Almighty Creator and their fellow man. As they share the water, they will also share our faith with the same message Jesus brought of living water in John 4:10.
PROJECT DETAILS AND TIMELINE
Project Scope: Deep borehole well with solar-powered electric pump and storage tanks, water distribution and hygiene training
Total Project Cost: $15,000 for materials and labor
Funding Requested: $15,000
Date Funding Required: June 9, 2025
Estimated Project Start Date: June 16, 2025
Estimated Project Completion Date: August 16, 2025
YOUR IMPACT
This project will probably have the greatest impact of the water projects completed in the Geita Diocese. Why? Because this village is in a very remote location and offers little to no opportunities for the people to [escape] the extremely impoverished conditions. This water project will offer tremendous hope for their future, especially the children. Once the water well is established, the parish can then start to plan for building a school. Then, the children will have a good education, which in turn opens the door to greater opportunities!
Access to clean, safe water, along with hygiene training, will reduce the number of illnesses.
| 50% COMPLETION REPORT | NYARUBELE | TANZANIA | |
| Report Submission Date: | September 15, 2025 | ||
| Estimated Project Completion Date: | October 10, 2025 | Has the Completion Date Changed Since Funding Was Approved?: | Yes |
| Total Project Costs from Beginning to End: | $17,500 | Have Costs Changed Since Funding Was Approved?: | Yes, but no additional funding from ILW |
| Latitude, Longitude: | -3.115278, 32.731667 | Has Location Changed Since Funding Was Approved?: | Yes |
Nyarubele has incurred a few setbacks.
The overrun on the budget is due to moving the location from the original spot to an area 2km from the original point. It will cost $800 for the labor to dig the trenches for the pipelines to be run back to the parish center, where the water storage tank is located.
The additional $1,700 is for the extra materials: piping, a larger pump, more solar panels, and a building to house the electrical equipment to operate the pump.
The new DD coordinates for the water well are -3.115278, 32.731667.
The new estimated completion date is October 10, 2025.
Through the grace of God, the Nyarubele Village water project reached its successful conclusion. The project was originally scheduled to begin on June 16, 2025, with a projected completion date of August 15, 2025, and a total budget of $15,000. Due to several unforeseen logistical and technical challenges detailed in this report, the project experienced a total delay of 143 days and a final budget overrun of $4,400. These additional costs were covered by additional funding through the Catholic Diocese of Pittsburgh, and Ingomar Living Waters did not incur additional costs over and above the original budget.
This project encountered a series of significant challenges and setbacks, some of which are described in the Interim Report above, including delayed fund transfers, a necessary relocation of the borehole well, and extended negotiations with local landowners. Additionally, the project required revised technical planning to ensure long-term sustainability, complex government authorizations for electrical power, and navigation through periods of national political and civil unrest.
THE CONSTRUCTION PHASE
As detailed in the Interim Report, the project start was delayed due to the time required for fund transfers. When drilling began at the initial site on July 29, 2025. and after reaching a depth of 130 meters without striking water, the team halted operations to conduct a technical reevaluation. It was determined that the site’s high elevation made it unsuitable for consistent, year-round water access. To ensure project sustainability, we relocated the borehole to a lower elevation in a rice field approximately 1.8 kilometers from the parish property. This strategic move successfully secured a reliable water source for the community, though the additional labor and plumbing materials were part of the cost overruns described above.
Negotiations with villagers and landowners
The new site, a farming parcel owned by an associate of Father Silas, was secured after the landowner agreed to sell the plot to the Diocese of Geita. Although some local opposition initially arose, Father Silas, Father David, and Bishop Kassala held productive meetings with the landowner, adjacent farm owners, and villagers to address their concerns. This collaborative effort led to a successful agreement, allowing the Diocese to purchase the necessary land. While this process added approximately one week to the timeline, it incurred no additional costs to the project budget, and the land acquisition was funded separately and is not included in the project’s financial report.
Revised Planning & Safety Measures
To ensure the safety, feasibility, and sustainability of the system, Bishop Kassala personally visited the site to review a new water survey. Based on this assessment, he approved continuing the borehole drilling at the newly acquired property.
The drilling was successfully completed on August 1, 2025, with the water table reaching a depth of 95 meters. While this modification ensured a reliable water source, the change in location and depth contributed to the increased project costs as described above.
Government Authorizations for Infrastructure
While the Interim Report initially suggested solar power, further engineering analysis revealed that solar panels would not generate sufficient energy to transport water across the 1.8 kilometer distance between the borehole and the storage tanks. Consequently, funds originally allocated for solar was reallocated to cover electrical permitting and installation costs. A significant four-month delay occurred while Father David worked with local government authorities to secure authorization for electrical power, as no existing lines were available at the site.
National Political and Civil Unrest
Following the national presidential elections on October 29, 2025, Tanzania experienced a period of significant contention. The resulting civil unrest in major cities led the government to implement a nationwide internet shutdown for several days. Increased military and police presence unfortunately resulted in several fatalities, creating an environment that stalled project progress.
Further, as the nation approached its Independence Day on December 9, 2025, rumors of renewed unrest led to additional safety precautions and logistical delays, further extending the project timeline.
| PROJECT COMPLETION REPORT | NYARUBELE VILLAGE | TANZANIA | |
| Report Submission Date: | February 3, 2026 | ||
| Actual Project Completion Date: | January 4, 2026 | Has the Completion Date Changed Since Funding Was Approved?: | Yes |
| Total Actual Project Costs from Beginning to End: | $19,400 | Have Costs Changed Since Funding Was Approved?: | Yes, although costs above Ingomar Living Waters’ $15,000 funding were covered by additional funding from two private donors. |
| Updated Estimate of the Number of People Who Actually Will Be Served Daily: | 3,210 | Has the Estimate Changed Since Funding Was Approved?: | No |
| Actual Measured Pump Capacity in Liters Per Minute (LPM) | 90 LPM | 23.7755 GPM | Depth of Well in Meters or Feet: | 95 Meters | 311.68 Feet |
| Actual Latitude, Longitude: | -3.115278, 32.731667 | Has Location Changed Since Funding Was Approved?: | Yes |
THE COMMISSIONING CELEBRATION
In this video, you can see the immense joy of the community as they sing and dance to celebrate this life-giving gift. One Swahili song poignantly translates to: “The donors, the bishop, and Bevi are the fruit of the church who brought new life to us through this water.”
Thank you!

All projects are made possible by World Changers.