NYARUBELE, TANZANIA

COMPLETE

STATUS

people impacted

dollars funded

FUNDED APRIL 30, 2025

Young girls fetching water for bathing and laundry

LOCATION

Nyarubele is a very small village with approximately 3,210 residents in the Geita Region of Tanzania.  The nearest airport is MWZ – Mwanza, located 77.6 km north of Nyarubele. Nearby towns include Kadasi (1.9km south) and Ligembe (7.4km east.) 
[Distances are “as the bird flies” and approximate.]

CURRENT CONDITIONS

St. Anthony of Padua Catholic Parish is in the village of Nyarubele. The parish priest, Father Silas Haki, explained the situation of the lack of water in Nyarubele. Since there is no source of clean water, the people must either buy water from the Kabaka hand-dug well or get [dirty, contaminated] water from ponds that are formed during the rainy season. The water from Kabaka is too expensive for most villagers, and they would need to travel 2-5 kilometers each way on foot or bicycle to get it (IF they own one!)  Note that hand-dug wells do not provide safe water because of contamination factors, and they dry up completely during dry season.

The Nyarubele people live in such severe poverty that few of them can afford to buy water or even travel to buy water. Most people are uneducated and sustain their families through small agricultural activities and raising livestock to consume and occasionally sell. They walk several kilometers to church, the ponds, and other places every day. A few people have simple bicycles for transportation, and even fewer own a motorized vehicle.

Nyarubele has a clinic. A St. Anthony parishioner is also the nurse at the local clinic. She reported that the people suffer from many waterborne illnesses. The most common are diarrhea, cholera, typhoid fever, dysentery, hepatitis A, amoebiasis, and E. coli. Diarrhea is the fourth leading cause of death in Tanzania. Since it is mainly women and young girls who are tasked with fetching water, they suffer [most] greatly.

Livestock share the dirty water source.

Current water used in Nyarubele

Health Center Statistics 

FUTURE MAINTENANCE AND REPAIRS

Father Silas Haki explained that currently, the parish is purchasing water from the Kabaka family-owned hand-dug well. This water must be boiled for several minutes before it is safe to drink. Mama Kanuti rides a bicycle to buy water. The parish uses approximately 120 liters of water per day. The cost is about 410,000 TSh ($155) per month. Once the water well project is completed, Father Haki will use the money currently being spent to purchase water to establish a maintenance fund. After several months of doing this, he will have his
maintenance fund. Since this village is truly “the poorest of the poor,” he will not be able to depend upon the parishioners or local people to sustain the funds. Also, for the protection of this water project, the distribution points will be only on parish property. However, it will be open to all who come for water. No one will be denied access to this clean water source, due to religious differences.

Children carry the heavy water home on their heads.

CHRISTIAN DISCIPLESHIP

The water distribution point for the well will bring people together from different walks of faith. Some will not know about the Gospel; some will know, but have doubts about a good and loving God that seemingly does not care for them, and some will come with their faith and trust in God. The people will sometimes interact, and the faithful will share their love for Our Almighty Creator and their fellow man. As they share the water, they will also share our faith with the same message Jesus brought of living water in John 4:10.

PROJECT DETAILS AND TIMELINE

Project Scope: Deep borehole well with solar-powered electric pump and storage tanks, water distribution and hygiene training

Total Project Cost:  $15,000 for materials and labor  

Funding Requested:  $15,000

Date Funding Required: June 9, 2025

Estimated Project Start Date: June 16, 2025

Estimated Project Completion Date: August 16, 2025

YOUR IMPACT

This project will probably have the greatest impact of the water projects completed in the Geita Diocese. Why? Because this village is in a very remote location and offers little to no opportunities for the people to [escape] the extremely impoverished conditions. This water project will offer tremendous hope for their future, especially the children. Once the water well is established, the parish can then start to plan for building a school. Then, the children will have a good education, which in turn opens the door to greater opportunities!
Access to clean, safe water, along with hygiene training, will reduce the number of illnesses.

 Proposed well site

INTERIM REPORT SEPTEMBER 15, 2025

50% COMPLETION REPORTNYARUBELETANZANIA
Report Submission Date:September 15, 2025
Estimated Project Completion Date:October 10, 2025Has the Completion Date Changed Since Funding Was Approved?:Yes
Total Project Costs from Beginning to End:$17,500Have Costs Changed Since Funding Was Approved?:Yes, but no additional funding from ILW
Latitude, Longitude:-3.115278, 32.731667Has Location Changed Since Funding Was Approved?:Yes

 

Nyarubele has incurred a few setbacks.

  1. The process of receiving and transferring the funds took longer than expected. The longest delay was in Denver, Colorado, because Father John Ludanha was out of the office on a retreat for two weeks. Therefore, the check was not deposited in Denver until July 16th, and then the funds weren’t wire transferred to Tanzania until July 21st.
  2. The materials were ordered, and the borehole drilling began at the designated site on Tuesday, July 29th. They drilled to a depth of 130 meters and still didn’t find water. The initial survey was done during the rainy season, while the aquifer was full; the drilling was done during the dry season, when the water aquifer was completely dry. It is good that the borehole well was not placed here.
  3. A suitable location was found approximately 2km from the parish property on a flat farming parcel owned by an individual, Mashaka Juma, known by the parish priest, Father Silas. Mr. Juma agreed to sell the small piece of land to the Diocese of Geita.
  4. Bishop Kassala visited the location on Thursday, July 31st.
  5. Borehole drilling was completed on Friday, August 1st. Water was found at 95 meters, and the well flashing was successful.

The overrun on the budget is due to moving the location from the original spot to an area 2km from the original point. It will cost $800 for the labor to dig the trenches for the pipelines to be run back to the parish center, where the water storage tank is located.

The additional $1,700 is for the extra materials: piping, a larger pump, more solar panels, and a building to house the electrical equipment to operate the pump.

The new DD coordinates for the water well are -3.115278, 32.731667.

The new estimated completion date is October 10, 2025.

COMPLETED FEBRUARY 3, 2026

Through the grace of God, the Nyarubele Village water project reached its successful conclusion.  The project was originally scheduled to begin on June 16, 2025, with a projected completion date of August 15, 2025, and a total budget of $15,000. Due to several unforeseen logistical and technical challenges detailed in this report, the project experienced a total delay of 143 days and a final budget overrun of $4,400.  These additional costs were covered by additional funding through the Catholic Diocese of Pittsburgh, and Ingomar Living Waters did not incur additional costs over and above the original budget.

This project encountered a series of significant challenges and setbacks, some of which are described in the Interim Report above, including delayed fund transfers, a necessary relocation of the borehole well, and extended negotiations with local landowners. Additionally, the project required revised technical planning to ensure long-term sustainability, complex government authorizations for electrical power, and navigation through periods of national political and civil unrest.

BEFORE

AFTER

THE CONSTRUCTION PHASE

As detailed in the Interim Report, the project start was delayed due to the time required for fund transfers. When drilling began at the initial site on July 29, 2025. and after reaching a depth of 130 meters without striking water, the team halted operations to conduct a technical reevaluation. It was determined that the site’s high elevation made it unsuitable for consistent, year-round water access. To ensure project sustainability, we relocated the borehole to a lower elevation in a rice field approximately 1.8 kilometers from the parish property. This strategic move successfully secured a reliable water source for the community, though the additional labor and plumbing materials were part of the cost overruns described above.

Negotiations with villagers and landowners

The new site, a farming parcel owned by an associate of Father Silas, was secured after the landowner agreed to sell the plot to the Diocese of Geita. Although some local opposition initially arose, Father Silas, Father David, and Bishop Kassala held productive meetings with the landowner, adjacent farm owners, and villagers to address their concerns. This collaborative effort led to a successful agreement, allowing the Diocese to purchase the necessary land. While this process added approximately one week to the timeline, it incurred no additional costs to the project budget, and the land acquisition was funded separately and is not included in the project’s financial report.

Revised Planning & Safety Measures

To ensure the safety, feasibility, and sustainability of the system, Bishop Kassala personally visited the site to review a new water survey. Based on this assessment, he approved continuing the borehole drilling at the newly acquired property.

The drilling was successfully completed on August 1, 2025, with the water table reaching a depth of 95 meters. While this modification ensured a reliable water source, the change in location and depth contributed to the increased project costs as described above.

 

Installation of Piping from Borehole to Distribution

Electrical Control Panel for Pump

Water Distribution Manifold

Government Authorizations for Infrastructure

While the Interim Report initially suggested solar power, further engineering analysis revealed that solar panels would not generate sufficient energy to transport water across the 1.8 kilometer distance between the borehole and the storage tanks. Consequently, funds originally allocated for solar was reallocated to cover electrical permitting and installation costs.  A significant four-month delay occurred while Father David worked with local government authorities to secure authorization for electrical power, as no existing lines were available at the site.

National Political and Civil Unrest

Following the national presidential elections on October 29, 2025, Tanzania experienced a period of significant contention. The resulting civil unrest in major cities led the government to implement a nationwide internet shutdown for several days. Increased military and police presence unfortunately resulted in several fatalities, creating an environment that stalled project progress.

Further, as the nation approached its Independence Day on December 9, 2025, rumors of renewed unrest led to additional safety precautions and logistical delays, further extending the project timeline.

Powerhouse with electricity

 

PROJECT COMPLETION REPORTNYARUBELE VILLAGETANZANIA
Report Submission Date:February 3, 2026
Actual Project Completion Date:January 4, 2026Has the Completion Date Changed Since Funding Was Approved?:Yes
Total Actual Project Costs
from Beginning to End:
$19,400Have Costs Changed Since Funding Was Approved?:Yes, although costs above Ingomar Living Waters’ $15,000 funding were covered by additional funding from two private donors.
Updated Estimate of the Number of People Who Actually Will Be Served Daily:3,210Has the Estimate Changed
Since Funding Was Approved?:
No
Actual Measured Pump Capacity
in Liters Per Minute (LPM)
 90 LPM  |  23.7755 GPMDepth of Well
in Meters or Feet:
95 Meters  |  311.68 Feet
Actual Latitude, Longitude:-3.115278,  32.731667Has Location Changed Since Funding Was Approved?:Yes

THE COMMISSIONING CELEBRATION

On January 4, 2026, after the project reached its successful conclusion, we celebrated with an opening ceremony! It was a true blessing to participate in such a beautiful celebration. Schoolchildren, villagers, and the faithful gathered to welcome the bishop and witness this milestone. For many, the highlight was finally collecting their very first bucket of clean, safe water.

In this video, you can see the immense joy of the community as they sing and dance to celebrate this life-giving gift. One Swahili song poignantly translates to: “The donors, the bishop, and Bevi are the fruit of the church who brought new life to us through this water.”

The first buckets of water were blessed by Bishop Kassala and used for the baptism of over 150 people. Your generous gift has done more than just provide the physical water necessary to sustain life; it has provided a “new life in Christ” for this entire community.

Bishop Kassala blessing water from well for baptisms

Additionally, Bishop Kassala expressed his deepest gratitude to the ILW donors and the volunteers who work tirelessly to bring clean water to those in need.

Thank you!